PRINCE2 History and Overview

By: Jim Owens PMP

I am often asked questions about the Prince2 methodology, so I thought I should jot down a few notes about it.

The project Management methodology PRINCE2 started life in 1975 as PROMPT2 (Project, Resource, Organisation, Management and Planning Technique) developed by Simpact Systems Ltd, a UK company. Four years later in 1979 PROMPT2 was adopted by another UK Company CCTA (Central Computer and Telecommunications Agency), now part of the Office of Government Commerce (OGC), who modified and renamed the methodology to PRINCE (Projects In Controlled Environments) in 1989, following input from around 150 European organizations, and used it as the standard methodology for all government information systems projects.

In 1996 CCTA released PRINCE2, as the standard methodology for managing all projects in the UK government

2005 saw the release of a significant update of the PRINCE2 documentation.PRINCE2 itself is actually in the public domain, so it is not restricted to a particular vendor, however there are many training organisations around to world to assist with accreditation.

There are two accreditation levels, "Foundation", a one-hour multiple-choice exam, and "Practitioner", a three-hour written exam. The Practitioner exam is open-book. Whist preparation courses are available around the world; they are not mandatory for attempting the exams.

Project managers often ask what the difference is between PMBOK (a guide to the Project Management Body Of Knowledge, the ANSI standard for project management, produced by PMI) and PRINCE2. You can think of it this way, PMBOK tells you what a project manager should know to manage a project successfully, PRINCE2 tells you what you should do.

There is often a misconception that PRINCE2 is applicable only to IT projects. Although that was the case in the early days, that is no longer true.

PRINCE2 is a process-driven project management method, but one of its weaknesses comes from its a high degree of scalability and applicability of modules that it can lead to a project becoming what has been dubbed a "PINO", a PRINCE In Name Only.

PROCESSES
---------

The PRINCE2 methodology comprises forty-five sub-processes organized into eight high level Processes. Each process has key inputs and outputs, together with the specific objectives, activities and documentation:

1.SU Starting Up a Project

2.PL Planning

3.IP Initiating a Project

4.DP Directing a Project

5.CS Controlling a Stage

6.MP Managing Product Delivery

7.SB Managing Stage Boundaries

8.CP Closing a Project

SU - Starting up a project
--------------------------
The project brief (charter) is formulated, including the outline scope of the project (what will be/not be included in the project) and its justification. This phase also appoints the team, and lays out the project management approach to be taken. Once this stage has been signed off by the Board, the preliminary project officially exists, but is not yet initiated.

PL - Planning a project
-----------------------
The activities necessary to produce the product of the project are identified. This is critical because the PRINCE2 methodology strongly recommends a product-based approach. Next, the effort for each activity is estimated and combined in a schedule. Risk are evaluated and recorded and planned for in the Risk Log, and the reporting format for the rest of the project determined.

IP - Initiating a project
-------------------------
The outouts of the previous stages are considered and enhanced to form a Business Case (a Business Case is mandatory for each project). Due consideration is given to the project management and controlling approach and quality standards to be followed. The Project Initiation Document (PID) is produced and submitted to the board for project authorisation.

DP - Directing a project
------------------------
This is where a lot of the "real" project management happens. Stages can be authorized, or the plans can be amended (and reauthorized) to allow for risk events, slippages, scope changes and so on. If a project has "gone wrong" and is unrecoverable, it is during this process that a decision to terminate may be made.

CS - Controlling a stage
------------------------
Projects, especially large or complex projects are often decomposed to stages, each stage being managed as almost a separate project. This stage also monitor progress and reports to the Board. Issues (actualized risks) from these stages are dealt with or (where predefined triggers are met) escalated to the Board.

MP - Managing product delivery
------------------------------
Work packages need to be executed, delivered and accepted (by comparison with the project plan, including the product scope statement and quality plan)

SB - Managing stage boundaries
------------------------------
A stage boundary is the final part of a stage, so when a project is divided into stages, this process defines what must happen towards the end of a stage and how the subsequent stage is auctioned (or current stage corrected, if it fails the quality checks). The information from the stage end is fed back through the communication plan.

CP - Closing a project
----------------------
Formally end the project and free up remaining project resources. Measure the degree of success of the project and record the Lessons Learned report produced for analysis of this project and for planning future projects. Officially accept the product of the project.

PHASES
------

PRINCE2 projects are usually in four PHASES:

1. Starting a project

2. Initiating a project

3. Implementation

4. Closing a project




Article Source: EZINEPRIME - FREE WEB CONTENT and ARTICLES

Jim Owens PMP is a career Project Manager, Presenter and PMP Instructor. Director of Certification with PMI W Australia, Columnist with www.PMHub.net and Information Age Magazine. Visit Jim at www.PromotePM.org The Home of Project Management. Jim's Domains & Web Hosting: www.WebsWoven.com



Add this article to your favorite Social Bookmarkers. Bookmark this Article using any bookmark manager


Print This Article Post Comment Add To Favorites Email to Friends Ezine Ready






More Related Articles on Project Management


Click here for more ARTICLE CATEGORIES






















 
Links
Links
Links
 
  Cool MySpace Layouts
Cool Friendster Layouts
 
Bite Me!

EzinePrime © 2006-2007 HubPrime.com
Notice: We collect personal information on this site. To learn more about
how we use your information, please see our Privacy Policy.

Home | About| Contact Us | PrimeLinks| Privacy Policy | Terms of Service | RSS
by  HubPrime
 
Creative Commons License
This work is licensed under a Creative Commons Attribution-Share Alike 3.0 License.
EuworxWordPress ThemesZwangDomantysDomantixFriendster LayoutsMySpace LayoutsEmjeiNeuro Patch
Jordan CreekSocial Media BlogT-CribiSurferStar SurfaceSmoovrFriendster LoungeAustinitesEkekekThe Grey LadyEthanol ConsultantsPee Em WatsonSwiss Pilates Swiss Pilates OrgWorld NewsGirl Power BlogBB ProCIE-SLG. Smith & CoGreen BytesHonigimmoLisa SantanaMommy MayRichdale NewburyportSandy Alderson Veterinarians Without BordersWolfgang PuckCranes For PeaceTouchDHeaven ELSWHere Jeff's Loop Leopard O'Web Open Book Peace Project TuniTec

Powered by Article Dashboard